ITEM 6-K
Council Meeting: July 25, 1989 Santa Monica, California
To: Mayor and City Council
From: City Staff
Subject: Award of Contract for 1988-89 Street Resurfacing Program
INTRODUCTION
This report recommends that the City Council award a contract for
the 1988-89 Street Resurfacing Program to Sully Miller
Contracting Co., the lowest responsible bidder, in the amount of
$759,199.51.
BACKGROUND
Each fiscal year, the City Council authorizes a City-wide street
resurfacing program which includes resurfacing, cold plane and
reconstruction intersections, slurry sealing and curb, gutter and
sidewalk construction/repair in various areas of the City. The
criteria used to determine which streets are to be resurfaced during
a given year are age, surface and subsurface condition, complaints
received, types of use (commercial or residential), traffic volumes, or
projected change of use or volume, etc.
The following streets are proposed to be resurfaced or slurry sealed
under the 1988-89 Street Resurfacing Program:
Street Limits
TO BE RESURFACED:
5th St. . . . . . . . Bay St. to Ocean Park Blvd.,
9th St. . . . . . . . Montana Ave. to San Vicente Blvd.,
20th St. . . . . . . . North of Santa Monica Freeway to Arizona Ave.,
Michigan Ave. . . . . Lincoln Blvd. to 14th St.,
Strand St. . . . . . . Main St. to 4th St.
TO BE SLURRY SEALED:
5th St. . . . . . . . Wilshire Blvd. to Montana Ave.,
5th St. . . . . . . . Ocean Park Blvd. to Hill St.,
9th St. . . . . . . . Santa Monica Blvd. to Wilshire Blvd.,
23rd St. . . . . . . . Montana Ave. to Wilshire Blvd.,
25th St. . . . . . . . Montana Ave. to San Vicente Blvd.,
Alta Ave. . . . . . . 4th St. to 7th St.,
Hollister Ave. . . . . Main St. to 3rd St.,
Oak St. . . . . . . . Euclid St. to 14th St.,
Pine St. . . . . . . . 17th St. to 18th St.,
Airport Infield Areas
INTERSECTIONS TO BE RECONSTRUCTED:
4th St. and Pico Blvd.
Main St. and Pico Blvd.
Main St. and Ocean Park Blvd.
Assessments
Council has initiated proceedings to assess commercial properties for
street resurfacing and gutter construction contiguous to these
properties. Commercial property owners are assessed for the full cost
of gutter construction (about $9.50 per lineal foot) and one-half the
cost of resurfacing (about $7.50 per square foot).
This is a cash assessment (no bonds will be issued). Unpaid
assessments are to be placed on the property owners' 1990-91 tax
bill. Assessments are expected to generate approximately $48,400 in
revenue. Residential properties will not be assessed.
Bid Package
The Notice Inviting Bids was published on June 13 and 14, 1989, in
the Evening Outlook and in four construction journals. The notice
was sent to four minority business associations and six contractors'
associations. Plans and specifications were issued to ten contractors
and subcontractors. Bids were opened and read publicly by the
Deputy City Clerk on July 7, 1989.
Five bids were received as follows:
Sully Miller Contracting Co. $759,119.51
Vernon Paving Company $784,510.64
Damon Construction Company* $828,171.16
Excel Paving Company $839,361.00
Goal/DBA Best Western Paving Co. $906,177.33
City Engineer's Estimate: $765,103.00
*WMBE Contractor
Sully Miller Contracting Co. has been the successful bidder for the
City's street resurfacing program for several years and staff has been
satisfied with their performance.
BUDGET/FINANCIAL ANALYSIS
Funds Required
Contract $759,119.51
Contingencies 26,903.02
Total Required $786,022.53
Appropriation authority for implementation of the 1988-89 Street
Resurfacing program is available as follows:
General Fund:
Street Resurfacing Program (01-770-421-000-965). . $391,755.53
Water Fund:
Resurfacing (25-770-421-000-947) . . . . . . . . . . . . . . 205,267.00
Wastewater Fund:
Resurfacing (31-770-421-000-960) . . . . . . . . . . . . . . 105,000.00
Airport Fund:
Airport Fund (33-710-631-000-903) 84,000.00
TOTAL FUNDS AVAILABLE . . . . . . . . . . . . . . . . . . . . . . $786,022.53
RECOMMENDATIONS
It is recommended that the City Council:
1. Award a contract for the 1988-89 Street Resurfacing Program to
Sully Miller Contracting Co., the lowest responsible unit price bidder,
in the amount of $759,119.51; and
2. Authorize the City Engineer to issue any change orders necessary
to complete additional work to the extent of funds available in
accordance with the Administrative Instruction on Change Orders.
Prepared by: Stanley E. Scholl, Director of General Services