ITEM 6-K
TO: Mayor and City Council
FROM: City Staff
SUBJECT: Recommendation to Award Contract for Alteration and Renovation
of the Marine Park Recreation Center to Facilitate Use as a
Child Care Center.
Introduction
This report requests the City Council award a contract, contingent upon City
Council approval of Item 11C, for alteration and renovation of Marine Park
Recreation Center for use as a child care center to Kevin Kraus Construction
Co., the lowest responsible bidder, in the amount of $298,100.00.
Background
In October of 1988, the City Council approved the use of a portion of the
Marine Park Recreation Center for a 3,000 square foot children's day care
center for children of City employees as well as residents of the City.
Plans for alteration and renovation of the facility were prepared by the
General Services Department, Civil Engineering Division in consultation with
an architectural firm specializing in child care center design and with a
local child care center director with expertise in infant care and State
licensing requirements.
A Notice Inviting Bids was published on October 31 and November 1, 1989, in
the Evening Outlook and in four construction journals. Bidding packages were
requested by eleven contractors and were also forwarded to eight
minority/small business contracting associations and one organized labor
council. While numerous bidding packages were requested, there was difficulty
in obtaining bids due to the nature and relatively small size of the project.
To obtain additional bids an Addendum was issued extending the bid opening one
week.
Bids were received, opened and publicly read on December 8, 1989. Six bids
were received as follows:
BASE BID
Kevin Kraus Construction Co. $248,750.00
M.S. Construction & Electrical Contractor $249,950.00
California IBA Inc. $329,785.00
J. Grothe Enterprises, Inc. $334,919.00
Cavecche Engineering & Construction Co., Inc. $390,168.00
Hugh F. Peters & Associates $399,999.00
City Engineer's Estimate $ 300,000.00
The bid documents required that contractors submit prices for seven Additive
Alternate items. Listed in Table 1 is a summary of the Additive Alternate Bid
items and prices by Contractor.
Staff recommends acceptance of the following Alternate items in the order
shown:
5A. Outdoor Storage Areas: These areas though outside the building are
incorporated into the basic building structure and of the same materials
as other work on the project. They are integral to outdoor functions and
equipment security.
1A Outdoor Play Equipment: Play equipment selected by the day care
consultant for the three specific age groups and developmental levels.
7A Outdoor Paving Area: All weather surface for games, tricycle riding and
various organizational and developmental functions. Provides containment
border for sand filled play areas.
Financial Impact
Funds required for the contract are as follows:
Base Bid $ 248,750.00
Additive Alternates 1A, 5A, 7A 49,350.00
Construction Contract Total $ 298,100.00
Contingencies 30,000.00
Total Funds Required $ 328,100.00
Appropriation authority in the amount of $279,015 is currently available for
this project in CIP Account Numbers 01-710-262-26590-8910-99177 ($85,100),
01-710-262-26589-8910-99177 ($143,915) and 53-740-511-26490-8923-99193
($50,000). Funds in the amount of $49,085.00 must be appropriated from
General Fund reserves to CIP Account Number 01-710-262-26590-8910-99177 to
complete funding for this project.
Recommendation
It is recommended that the City Council:
1. Award a contract, contingent upon City Council approval of Item 11C, for
alteration and renovation of the Marine Park Recreation Center to Kevin
Kraus Construction Co., the lowest responsible bidder, in the amount of
$298,100.00;
2. Appropriate funds in the amount of $49,085.00 from General Fund reserves
to CIP Account Number 01-710-262-26590-8910-99177 to complete funding for
the project; and
3. Authorize the City Engineer to issue any change orders necessary to
complete additional work to the extent of funds available in accordance
with Administrative Instruction on Change Orders,
Prepared by: Stan Scholl, Director of General Services
Desi Alvarez, City Engineer