ITEM 6-M

Council Meeting: August 9, 1994          Santa Monica, California

TO:        Mayor and City Council
FROM:      City Staff
SUBJECT:   Award of Contract for Storm Drain Improvements,
           Sanitary Sewer Main Replacements, Sanitary Sewer Main
           Relining and Water Main Replacements at Various City
           Locations

Introduction

This report recommends that the City Council award a contract for
storm drain improvements, sanitary sewer main replacements,
sanitary sewer main relining and water main replacements at
various City locations to Colich & Sons, the lowest responsible
bidder, in the amount of $1,788,401.31.

Background

During the FY 1992-93 and 1993-94 budget process, the City
Council appropriated funds for storm drain improvements, sanitary
sewer main replacements, sanitary sewer main relining and water
main replacements at various locations in the City.

The storm drain improvements will replace the existing limited
capacity drywells (holes in the ground covered by metal grates)
located in alleys throughout the City with larger concrete catch
basins which connect directly into the Los Angeles County storm
drain.  Thus, water ponding in alleys and the costs of processing
water which overflows into alley sewer drains will be alleviated.

The sanitary sewer main replacements will replace sanitary sewer
mains which have deteriorated due to age, are corroded and
cracked.  The proposed locations were recommended for replacement
by the City's Sanitary Sewer Master Plan (prepared by CH2M Hill
in 1992), and confirmed by the City's Wastewater Division.

The sanitary sewer main relining work will take place in areas
where the wastewater lines are inaccessible for equipment
necessary for open trench operations (such as narrow alleys and
rear yard easements on private property), where lines are
severely deteriorated due to age and corrosion, and where
replacement is not needed since it does not require additional
sanitary sewer capacity.  Relining consists of inserting a pipe
lining system into an existing wastewater line which results in
improved flow, fewer sewer back-ups and prolonged service life of
the lines.  The water main replacement will upgrade the existing
system to improve water pressure in the area and provide better
fire flows in the area.


A Notice Inviting Bids was published on June 27 and June 28,
1994, in The Outlook, as well as in four construction journals. 
In addition, bidding documents were sent to six women/minority
business enterprise associations (WMBE).  Bidding packages were
requested by 25 contractors.  The City Clerk's office received
nine sealed bids, which were publicly opened and read aloud  on
July 25, 1994 by the Deputy City Clerk.

     The base bid results were as follows:

      1.  Colich & Sons                      $1,788,401.31
     +2.  ARNO Construction Co.              $1,851,675.00
      3.  Mladen Buntich Construction        $1,876,569.00
      4.  Williams Supply Company            $1,910,109.00
     +5.  Mike Masanovich Const.             $1,931,970.50
     *6.  Miramontes Construction            $1,996,388.00
      7.  Granite Construction               $2,145,001.80
     +8.  Mike Prlich & Sons                 $2,146,436.00
     *9.  Valverde Construction Inc.         $2,356,882.00

               City Engineer's Estimate  . . $2,110,000.00

*  WMBE
+  Non-responsive

Three bids did not include a requested price for Alternate 1, an
optional method of sewer and water line installation, and are
considered non-responsive.  The lowest bidder, Colich & Sons,
supplied the City with references and all references reported that
the contractor's work was satisfactory.  The State Contractors'
License Board verified that the Contractor's license is current,
active and in good standing.

Budget/Financial Analysis

FUNDS REQUIRED

          Contract .. . .. . .. .  $1,788,401.31
          Contingencies (10%).. .  $  179,098.69

                             TOTAL $1,967,500.00

Funds are available in CIP account numbers:

                                 Contract      Project           
Account Number                    Amount     Contingency      Total   

31-760-661-20092-8900-99208   $363,281.80    $36,328.18   $399,609.98
31-760-661-20093-8900-99208   $ 84,084.86    $ 8,408.49   $ 92,493.35
31-760-661-20092-8900-99120   $252,050.75    $25,205.07   $277,255.82
31-760-661-20093-8900-99120   $594,366.90    $59,436.69   $653,803.59
31-760-661-20093-8900-99125   $278,585.00    $27,858.50   $306,443.50
25-760-671-20093-8900-99136   $216,032.00    $21,861.76   $237,893.76


                    Total:  $1,788,401.31   $179,098.69     $1,967,500.00

Recommendation

It is recommended that the City Council:

1.    Award a contract to install storm drain improvements,
      sanitary sewer main replacements, sanitary sewer main
      relining and water main replacements at various City
      locations to Colich & Sons, the lowest responsible bidder,
      in the amount of $1,788,401.31.

2.    Authorize the City Engineer to issue any necessary change
      orders to complete additional work in conformance with the
      Administrative Instructions on change orders.

Prepared by:   Craig Perkins, Director of Environmental Public
                 Works Management Department
               Anthony Antich, City Engineer
               John Mundy, Utilities Manager