Item 6-CC
Council Meeting: August 11, 1998 Santa Monica, California
TO: Mayor and City Council
FROM: City Staff
SUBJECT: Recommendation to Authorize the City Manager to Negotiate and Execute a Change Order to Professional Services Contract No. 6522 (CCS) for the Municipal Bus Lines Facility Expansion Master Plan
Introduction
This report recommends that the City Council authorize the City Manager to negotiate and execute a Change Order to Professional Services Contract No. 6522(CCS) with RNL/Interplan for the Municipal Bus Lines Facility Expansion Master Plan for an amount not to exceed eighty thousand dollars ($80,000).
Background
In late 1996, Council awarded a contract to RNL/Interplan in the amount of $175,000 for the Facility Expansion Master Plan for the Santa Monica Municipal Bus Lines. The work has progressed through the following phases:
Phase I Programming
Review and evaluation of current operations and facilities to identify space needs, functional requirements, and adequacy of the facility for the Santa Monica Municipal Bus Lines operations.
Phase II Facility Analysis
Analysis of the adequacy of existing buildings and site in light of the future needs of SMMBL.
Phase III Master Planning
Development of a conceptual design layout of the facility to address the programmatic and facility needs assessment issues identified during Phase I and II.
Phase IV Implementation and Phasing Plan
Preparation of an Implementation and Phasing Plan to provide the City with an understanding of the distinct work elements that are necessary to carry out the Master Plan, including a proposed implementation schedule.
Phase V Cost Estimates
Provision of cost estimates for the proposed improvements and new construction. These estimates include the costs for design, construction, permits, phasing, relocation during construction, and other related project costs.
DISCUSSION
In the process of finalizing the draft Master Plan for the SMMBL Expansion, it became clear that a series of alternate schemes, not originally anticipated in the scope of work, need to be explored. These include options for an on-site public parking structure, a new lease facility at the 507 Olympic Boulevard site, and modifications to the 612 Colorado Avenue building. RNL/Interplan will be called upon to analyze these additional schemes carefully, as they will have substantial affect on project phasing, timing and cost.
As the Master Plan progresses through the EIR process, there will also be a need for the consultant to provide certain concept design plans to clearly define the environmental impact of the Plan.
BUDGET/FINANCIAL IMPACT
Funds in the amount of $90,000 are available in CIP Account #41-750-657-20095-8900-99104 "Transportation Facility Improvements" as follows:
Change Order to Contract 6522(CCS).......................$80,000
Contingency...............................................................$10,000
Total......................$90,000
RECOMMENDATION
Staff recommends that the City Council:
1. Authorize the City Manager to negotiate and execute a change order to Professional Services Contract No. 6522(CCS) with RNL/Interplan in an amount not to exceed $80,000 for the Santa Monica Municipal Bus Lines Master Plan; and
2. Authorize the City Engineer to issue any necessary change orders to complete additional work in conformance with the Administration Instructions on change orders.