COUNCIL MEETING: January 22,2002
Santa Monica,
California
TO: Mayor and City Council
FROM: City Staff
SUBJECT: Amendments to Existing Professional Services Contract No. 7742 (CCS)
for Geotechnical and Engineering Report Review and Related Services
INTRODUCTION
This staff report recommends that
the City Council authorize the City Manager to
negotiate and execute an amendment of $130,000 for Contract No. 7742 (CCS)
with Bing Yen and Associates for the review of geotechnical and engineering
geology reports for the Building and Safety Division.
BACKGROUND
Due to liquefaction potential and
other geologic hazards, state law mandates that the City require, review and approve geotechnical
and/or engineering geologist reports prior to construction permitting on most
major projects. The reports must demonstrate geotechnical feasibility and
appropriate mitigation of any seismic related hazards. By law, the City must use licensed
geotechnical engineers and engineering geologists to review and approve the
feasibility and mitigation reports. Bing Yen & Associates has provided
these review services during the previous and current fiscal year.
Staff originally requested
qualifications from five geotechnical engineering firms for review of
geotechnical reports. On June 27, 2000, Council authorized a contract for
geotechnical services with Bing Yen and Associates in the amount of $60,000. On
July 24, 2001, Council authorized an amendment to the contract of $60,000 for
fiscal year 01/02 for a total contract amount of $120,000.
DISCUSSION
Additional professional services for
geotechnical review will be necessary beyond what staff anticipated for FY
01/02 due to the increase number of complex projects submitted. This requires
amending the contract with Bing Yen and Associates for an additional $130,000
to provide services through June 30, 2002.
BUDGET/ FINANCIAL IMPACT
The Building and Safety Division
collects user fees to reimburse the General Fund expenditures for review of
geotechnical and engineering geology reports. On April 24, 2001, Council passed
new user fees for the review of engineering reports. Pursuant to state law,
these new fees became effective June 25, 2001. These fees cover the cost of
providing these services.
Originally, the estimated revenues
in FY 01/02 for the review of engineering reports was $50,000. An additional $150,000 above the budget projection
is anticipated this fiscal year, which will cover the expenses for the contract
amendment.
Staff recommends an additional
budget appropriation of $130,000 be approved at account number 0321.555060 and
a net budget increase of $150,000 be made to the appropriate revenue accounts (
a budget increase of $200,000 to revenue account 01321.400560 and a budget
decrease of $50,000 made to revenue account 01321.400500).
RECOMMENDATION
Staff recommends that the City
Council authorize the City Manager to negotiate and execute an amendment to
Contract No.7742 (CCS) with Bing Yen & Associates for $130,000, for a new
not-to-exceed total amount of $250,000, and approve the recommended budget
changes specified in the Budget/Financial Impact section.
Prepared by:
Suzanne Frick, Director, Planning and Community Development
Timothy P. McCormick, P.E., Building Officer
Manuel M. Mendizabal, S.E., Plan Check Supervisor