Contract
Amendment with Law Engineering and Environmental Services, Inc. for
Additional Geotechnical Inspection Services |
Introduction
This report recommends that City Council authorize
the City Manager to negotiate and execute an amendment to Contract 7648 (CCS)
with Law Engineering and Environmental Services, Inc. in an amount not to
exceed $45,710 and approval of $7,000 in contingency for additional
environmental and geotechnical inspection services for the Public Safety
Facility project.
Discussion
On November 18, 1999, a professional services
agreement was issued to Law Engineering and Environmental Services, Inc. for
environmental and geotechnical inspection services for the Public Safety
Facility project in the amount of $49,983. Their scope of work was determined
through initial boring samples. Actual experience during construction revealed
greater complexity and debris presence than anticipated. As the project
progressed, amendments to the Law Engineering agreement to provide for the
required additional inspection, testing, engineering consultation and
environmental services have been approved in the amount of $181,032. A final
amendment for services provided to meet City requirements is necessary.
Budget/Financial Impact
FUNDS
REQUIRED:
|
|
Contract |
|
$45,710 |
|
|
|
Contingency |
|
$ 7,000 |
|
|
|
|
|
|
|
|
|
Total Required |
|
$52,710 |
|
Funds in the amount of $52,710 are available in
account C01005800.589000, “Public Safety Facility Construction.”
Recommendation
Staff recommends that the City Council:
1.
Authorize the City
Manager to negotiate and execute an amendment to Agreement 7648 (CCS) with Law
Engineering and Environmental Services, Inc. for additional geotechnical and
inspection services for the Public Safety Facility project in an amount not to
exceed $45,710 and approve $7,000 in contingency; and
2.
Authorize the City
Engineer to issue any necessary Change Orders to complete additional work in
conformance with the Administrative Instructions on Change Orders.
|
Prepared
by: |
Craig Perkins, Director of
Environmental and Public Works Management Anthony Antich, P.E., City
Engineer Lauren Friedman, Senior
Architect, Project Manager |