Item 8-A

 

Council Meeting: October 8, 2002                                               Santa Monica, California

 

TO:                  Mayor and City Council

 

FROM:            City Staff

 

SUBJECT:      Presentation of Design Concepts and Award of a Design-Build Pre-construction Services Agreement, Including Renovation of the Existing Administration Building for the Big Blue Bus Campus Expansion Project, Phases II-IV

 

 

Introduction

This report describes the concept design plan for the Big Blue Bus (BBB) campus expansion project, phases II-IV. It also recommends that the City Council authorize the City Manager to negotiate and execute a design-build pre-construction services agreement, including renovation of the existing Big Blue Bus administration building, with Swinerton Builders in a total amount not to exceed $400,000 and approve a contingency of $60,000.

 

Background

On February 27, 2001, Council approved the Master Plan, certified the Final Environmental Impact Report for the BBB campus expansion project, and authorized staff to proceed with the program.

 

The overall program envisions project delivery in four main phases:

I) . As part of the planned expansion of the BBB, a portion of the bus fleet and support vehicle fleet will be converting to alternative fuels, such as Liquefied Natural Gas (LNG), Compressed Natural Gas, (CNG) and electric operation.  The first phase of implementation of the BBB Master Plan calls for cConstruction of a Natural Gas Fueling/Bus Wash Facility (LNG fuel for buses, CNG for other fleet vehicles), (You might want to mention the status of this portion)

II)   Demolition of the 612 Colorado building and construction of a new administration building with a below grade parking structure,

III)   Construction of a heavy-duty transit bus maintenance facility, and

IV) Demolition of the existing maintenance facility, grading, paving, and other site improvements.

 

At its August 14, 2001 meeting, Council awarded a construction contract to Mallcraft, Inc. for Phase I of the project, which is the Natural Gas Fueling, coin collection, and bus wash facility.   Phase I is currently under construction and scheduled for completion in spring of 2003. On September 11, 2001, Council awarded a design contract to Hellmuth, Obata + Kassabaum, Inc. (HOK) for the design of Phases II-IV. The concept design is currently underway.

 

Discussion

Concept Design Presentation

The best description of the concept design is expressed by HOK as follows: “The Santa Monica Big Blue Bus is an organization on the move.  It is a forward thinking organization that skillfully balances its state-of-the-art transit services with community-friendly teamwork. This will be evidenced in the new Big Blue Bus Campus Expansion

Project. The design is intended to capture the spirit of this progressive organization, while meeting the need for administration, operations and vehicle maintenance facilities.

 

Public art, distinguished architecture and sustainability concepts are being fully integrated into the design of the project through a highly collaborative and interactive process.  Through the use of elegant, yet expressive forms and materials, the design speaks to the character of this organization that is on the move.” 

 

The simplicity and clarity of the overall site plan and building organization supports the modern, efficient operations of the Big Blue Bus.  The landscaped courtyard at the heart of the project provides an outdoor place for gathering and public interaction. The lightness and transparency of the structural system and building envelope symbolize the openness of the institution. This envelope is meant to convey a sense of movement, and is conceived as an interactive “skin” rather than an enclosure. It allows the complex to functionally respond to climatic and environmental changes. At the same time, it projects artistic ideas that are meant to change perceptions, provoke thought, inform and educate. The bold, folded planes and dramatic sweeping arcs impart a dynamic character to the form of the building.   The use of a single vocabulary of materials, both durable and refined, for the entire complex portrays an organization that is diverse yet unified in its mission; innovative yet practical; truly a smart design.

 

The Santa Monica Big Blue Bus complex will be both flexible and enduring.  It will reflect the organization’s role as a responsible leader in the transit field that creates and maintains a quality living environment in Southern California.

 

As to sustainable design features, the City is seeking a LEEDS silver or gold rating for the facility. In addition to providing an on site alternative fueled vehicle station, elements to be explored and incorporated into the design as feasible include:

 

 

 

Dan Corson, project artist has several design concepts to present, including a L.E.D. display module for a portion of the new administration façade along Colorado Avenue; a movable vignette screen at the bus stop on Colorado Avenue, near Seventh Street; helical colored skylights along the maintenance building roofline on Seventh Street, and an intense colored reflective glass panel system incorporated into a portion of the administration building façade.

 

An open house meeting with the public was held the first week of October to receive input on the project design concepts.  Feedback received was extremely positive.

 

 

Modified Design-Build Approach

It was originally contemplated that the BBB Campus Expansion Project would be implemented using a design-bid-build approach, wherein the owner City provides the construction contractor drawings and specifications.  If adjustments to the drawings and specifications are needed, the cost associated with the resolution of such changes is typically the responsibility of the City. Additionally, the construction schedule is lengthened by the time required to address these changes.  It is not uncommon in the construction industry that projects delivered by the design-bid-build delivery method experience cost increases and the project construction schedule is lengthened. 

 

In an effort to limit unanticipated costs, expedite the construction schedule, and build a cohesive project team, this project will be implemented using a modified design-build approach.  Under the modified design-build approach, the design-builder will warrant to the City that it will produce design documents that are complete and free from error.  In addition, this approach allows the City to seek a guarantee on the construction costs (a Guaranteed Maximum Price (GMP) contract), wherein the City will know the construction costs before it finally commits to the construction of the project.  This is because the design-builder will be estimating the construction costs as the design is evolving.

There are several benefits to this approach:

 

1)     Warranty - The design-builder warrants to the City that it will produce plans that are complete and free from errors. This allows the City to negotiate a Guaranteed Maximum Price (GMP) contract.

2)     Timesavings – The project completion timeline is shortened as design and construction are allowed to overlap, while bidding periods and redesign are eliminated. The design-builder can begin material procurement and construction before the construction documents are fully complete.

3)     Cost-savings – The project can be completed for a lower over-all cost because of the time-savings achieved through a design-build approach.

1)Also inherent in this approach are savings created by certainty of timing of the project.  In design-build, design and construction are overlapped, bidding periods and redesign are eliminated, thus allowing total design and construction of the project to be more accurately determined and reduced.  The design-builder can begin materials/equipment procurement and construction work often begins before the construction documents are fully completed.  The resulting time savings typically translates into lower costs and a more predictable completion of construction.

 

The BBB campus expansion project will further benefit from the modified design-build approach through the assignment of the architect HOK, to team with the design-builder.  The City contract with HOK will be assigned to the design-builder once a GMP contract including a schedule of performance has been executed and the design of the BBB campus expansion project has been approved. 

 

Pre-construction Services Agreement

Staff recommends entering a two-phased agreement with the design-builder. The first phase would be a pre-construction services agreement, which would allow the design-builder to participate with the project team during the schematic and design development phases prior to the establishment of a GMP contract. During the pre-construction phase, the design-builder would provide services such as cost estimating, value engineering, constructability review, and assisting in the development of a construction schedule. Staff also recommends that the design-build firm perform the repair and renovation of the existing administration building at 1660 Seventh Street during this phase. This work is necessary to relocate BBB staff prior to the demolition of the 612 Colorado building and allow for construction of the new administration building at that location. It is imperative that this work be done by the design-builder now to comply with the current construction schedule.

 

The second phase would consist of finalizing the design and other construction documents, and providing construction services.  Upon completion of the design development, staff will recommend to Council a GMP and award of the second phase of the design-builder's agreement.  Approval of the project, including review by City Council, Planning Commission, Architectural Review Board, and Arts Commission will be a condition precedent to the payment of any construction related fees. 

 

 

 

 

Selection of Design-Builder

On February 11, 2002, a Request for Bids (RFB) for design-build services was prepared and distributed to thirteen firms.  The RFB was published in the “California Section” of the Los Angeles Times.  On March 13, 2002, the City received responses from four firms, which were evaluated by a Sselection Ccommittee including representatives from the BBB and Environmental and Public Works Management.  Each of the four firms that submitted a response to the RFB was asked to participate in an interview. The cost of Swinerton's proposal is below the average of the four firms.  The Selection Committee unanimously recommends Swinerton Builders for this project on the basis of the City's best bidder criteria, as set forth in Santa Monica Municipal Code Section 2.24.072, as follows: 

 

1.         Swinerton Builders submitted a competitive price for fees related to pre-construction services, and construction fees of the general contractor;. 

2.         Swinerton Builders Swinerton Builders team has extensive experience and is an industry leader in construction;

3.         Swinerton Builders Swinerton Builders has an excellent track record in the development of projects;. 

4.         Swinerton Builders Swinerton Builders has proven methods for completing projects in a timely manner;. 

5.         Swinerton Builders Swinerton Builders has strong financial resources to complete the project;. 

6.         Swinerton Builders Swinerton Builders has a reputation for character and integrity in the development of their projects; and

7.         Swinerton Builders Swinerton Builders has presented an experienced project development and construction management team that will be critical if the project is approved and moves forward with construction.  Swinerton Builders' qualifications and previous project experience include construction of the Santa Monica Municipal Pool, the Howard Hughes Center, Building 7, the DreamWorks Animation Campus, and the Arboretum Courtyard. In addition, it has experience in design-build projects at the LAX Gateway Enhancements and the UCI Recreational Center; and participation in projects with significant sustainable design components such as the Gap Corporate Campus, demonstrates their ability and expertise in the various aspects necessary for the successful completion of the BBB Campus Expansion Project. 

 

Staff contacted references which all reported that the work performed by Swinerton Builders is excellent.  The California State Contractors’ License "Board verified the license is current, active, and in good standing.  Staff also contacted the Center for Contract Compliance and found Swinerton capable of handling labor compliance issues. 


Budget/Financial Impact 

FUNDS REQUIRED:

 

Contract

 

$400,000

 

 

Contingency

 

$   60,000

 

 

 

 

 

 

 

Total Required

 

$460,000

 

 

Funds in the amount of $460,000 are available in account C41010401.589000, “Facility Improvements.”  

 

The total project (Phases I-IV) is estimated to cost approximately $86.5 million. Phases II-IV, which will be constructed by Swinerton, is estimated at $52 million.  Funds for this project are included in existing CIP accounts or reserved by the MTA for this project. 

 

Recommendations

Staff recommends that the City Council:

  1. Review the design concepts for the Big Blue Bus Campus Expansion Project and provide feedback to staff as appropriate; and
  2. Award a design-build pre-construction services agreement for the project, including renovation of the existing administration building to Swinerton Builders in a total amount not to exceed $400,000 and approve $60,000 in contingency funds; and
  3. Authorize the City Engineer to issue any necessary change orders within budget authority in accordance with the Administrative Instructions on Change Orders.

 

Prepared by:  Craig Perkins, Director of Environmental & Public Works Management

Anthony Antich, P.E., Manager, EPWM Engineering & Arch. Division

                        Stephanie Negriff, Director of the Big Blue Bus

Janeene De Martinez, Assistant Director of the Big Blue Bus - Transit Finance and

 Business Services

Roy Neva, Transit Construction Manager

                        Dave Britton, P.E., Principal Civil Engineer