Council
Meeting: June 22, 2004 Santa Monica, California
TO: Mayor
and City Council
FROM: City Staff
SUBJECT: Construction Contract for SAMOSHEL Facility
Upgrade
Introduction
This report recommends that City Council award a construction contract
for the upgrade to SAMOSHEL with AWI Builders, Inc. the best bidder, in the
amount of $441,020 and approve a contingency amount of $44,100 (10%).
Background
The SAMOSHEL Homeless Shelter was constructed in 1994 as a 100-bed emergency shelter for homeless in Santa Monica. The 7,800 square-foot tension fabric structure houses bunk beds, restrooms, counselor offices, sitting areas, kitchenette and a dining area. Occupants are allowed to reside in the shelter for up to 6 months, during which time they can receive counseling, apply for employment and locate permanent housing.
On November 13, 2001, Council approved using Federal
Community Development Block Grant (CDBG) funds to complete the first phase of
necessary upgrades including replacing the skin of the tension structure and
adding an air conditioning system and insulation. In Fiscal Years 2001/02 and 2002/03, funds were approved for additional
upgrades to ensure that the facility could continue to effectively serve its
clients. JCCA Design Consultants were
hired to provide architectural and engineering design services related to this
second phase of upgrades including constructing a commercial grade kitchen,
constructing full height partitions separating the various uses in the facility
and installing a sprinkler and fire alarm system to meet life/safety
requirements, and the project is ready to construct.
A Notice Inviting Bids for the construction contract was published
on April 1 and 3, 2004 in The Los Angeles Times. The bid package was
sent to eleven public plan rooms including five women/minority business
enterprise associations. Six contractors requested the bid package and the City
Clerk's office received one sealed bid, which was publicly opened on April 19,
2004 by the Deputy City Clerk.
The bid result was as follows:
AWI
Builders, Inc. $441,020
Architect’s
Estimate $315,000
Other contractors who purchased bid packages
were contacted and indicated that they did not submit bids because of workload
or difficulty obtaining prices from subcontractors. The contractors contacted also indicated that the current
construction market has been greatly impacted by the increased cost of
materials and workers compensation insurance.
rices, since CWS Inc., one of the
non-bidding contractor’s confirmed their estimate was $467,270.59, $26,250.59
higher than the bid submitted by AWI Builders.
As the current costs of construction continue to increase, there is no
evidence that re-bidding the project would result in lower bids.
AWI Builders, Inc. supplied the City with six references, all of which reported that the contractor's work quality was good and that the work was completed in a timely and cost efficient manner. AWI Builders, Inc. recently successfully completed Animal Shelter Improvements for the City of Santa Monica and is currently recommended to construct Woodlawn Cemetery improvements. The State Contractors' License Board verified that the Contractor's license is current, active, and in good standing.
Budget/Financial Impact
CONSTRUCTION
FUNDS REQUIRED:
|
|
Contract |
|
$441,020 |
|
|
|
Contingency |
|
$ 44,100 |
|
|
|
|
|
|
|
|
|
Total Required |
|
$485,120 |
|
Funds
are available in the following accounts:
|
|
C19069202.589000 |
|
$ 55,438 |
|
|
|
C19069203.589000 |
|
$214,979 |
|
|
|
C19003998.589000 |
|
$ 58,891 |
|
|
|
C19041704.589000 |
|
$100,000 |
|
|
|
C19067301.589000 |
|
$ 55,812 |
|
|
|
|
|
|
|
|
|
Total Available:
|
$485,120 |
|
|
Recommendation
Staff recommends that the City
Council:
1.
Award a
construction contract for the SAMOSHEL Facility Upgrade with AWI Builders, Inc.
the best bidder, in the amount of $441,020 and approve a contingency amount of
$44,100 (10%); and
2.
Authorize
the City Engineer to issue any necessary change orders to complete additional
work within budget authority.
Prepared by: Craig Perkins, Director, Environmental and Public Works Management
Anthony
Antich, P.E., City Engineer
Barbara
Stinchfield, Director, Community and Cultural Services
Karen
Ginsberg, Assistant Director, Community and Cultural Services
Tracy
Scuggs, Human Services Supervisor
Lauren
Friedman AIA, City Architect
Miriam
Mulder, Architect
Sam
Aslanian AIA, Architectural Associate