Meeting: September 28, 2004 Santa Monica, California
TO: Mayor
and City Council
FROM: City Staff
SUBJECT: Award of Contract for Franklin
Street Reservoir Roof Strengthening
Introduction
This report recommends that City Council
award a construction contract for strengthening of the Franklin
Street Reservoir Roof to Denboer Engineering and Construction, Inc., the best bidder, in the amount of
$279,500 and approve a contingency amount of $27,950 (10%).
Background
The
City Council appropriated funds in fiscal year 2004 to structurally
rehabilitate the roof slab of the Franklin Street Water Reservoir, which was built
in the late 1940’s. The pavement on top
of the Reservoir shows signs of distress and has inadequate steel
reinforcement.
Discussion
A
Notice Inviting Bids for the construction contract was published on July 15 and
17, 2004 in The Los Angeles Times and the F.W. Dodge newsletter. Six contractors requested bid packages and
the City Clerk's office received four sealed bids, which were publicly opened
on August 5, 2004 by the Deputy City Clerk.
The
bids received for this project are as follows:
Denboer
Engineering & Construction, Inc. $279,500
G.B.
Cooke, Inc. $321,000
R.J.
Bullard Construction, Inc. $342,750
Spiess
Construction Co., Inc. $355,000
City
Engineer's Estimate $360,000
The best bidder, Denboer Engineering & Construction, Inc. supplied
the City with four references, all of which reported that the contractor's work
quality was good and that the work was completed in a timely and cost efficient
manner. Denboer Engineering &
Construction, Inc. recently successfully completed repair work on the Lido Isle
Bridge in Newport Beach, the Foothill Reservoir and Retaining Wall in the City
of Tustin and the Mole Pier South, for Department of the Navy. Staff also contacted the Center for Contract
Compliance and found Denboer
Engineering & Construction, Inc. in good standing and capable of handling labor compliance issues.
The California Contractors’ State License Board verified that the Contractor's
license is active and in good standing.
Budget/Financial Impact
FUNDS
REQUIRED:
|
|
Contract |
|
$279,500 |
|
|
|
Contingency |
|
$ 27,950 |
|
|
|
Total Required |
|
$307,450 |
|
|
|
|
|
|
|
Funds,
in the amount of $307,450 are available in the account C250868.589000, “Franklin Reservoir Rehabilitation”
Recommendation
Staff recommends that the City
Council:
1.
Award a
construction contract for the Franklin
Street Reservoir Roof Strengthening project to Denboer
Engineering & Construction, Inc., the
best bidder, in the amount of $279,500 and approve a contingency amount of
$27,950; and
2.
Authorize
the City Engineer to issue any necessary change orders to complete additional
work within budget authority.
|
Prepared by: |
Craig
Perkins, Director, Environmental and Public Works Management Anthony Antich, P.E., City
Engineer Gil
Borboa, Water Resources Manager Bob
Harvey, Water Production/Treatment Superintendent Dave
Britton, P.E., Principal. Civil Engineer Eugenia Chusid, Civil Engineer Associate |