EPWM:CP:BJ:RB:/ICFConsulting.doc
Council
Meeting: September 28, 2004 Santa
Monica, California
TO: Mayor
and City Council
FROM: City
Staff
SUBJECT: Amendments to Contract #127(CD) with ICF
Consulting for Environmental Assessment and Remediation Activities at the City
Corporation Yard
INTRODUCTION
This report
recommends that the City Council authorize the City Manager to negotiate and
execute an amendment to Contract #127(CD) with ICF Consulting for additional
environmental assessment and remediation activities at the City Corporate Yard
in the amount of $54,990.
BACKGROUND
On September 12,
2000, the City Council approved funding in the amount of $2,207,233 for
Contract #127(CD) with ICF Consulting to conduct environmental investigation
and remediation services at the Airport, Big Blue Bus Yard, and the City
Corporate Yard. On March 11, 2003, the
City Council approved a contract modification in the amount of $230,000 for
additional environmental services at the City Yard. On January 13, 2004, the City Council approved a contract
modification in the amount of $341,370
to extend the existing agreement associated with environmental investigation
and remediation services at the Big Blue Bus Yard and the City Corporate
Yard.
DISCUSSION
The proposed contract
modification to 127(CD) with ICF continues the existing contractual
relationship with ICF for environmental assessment and remediation services at
the Corporate Yard through October 2004.
This work includes remediation of subsurface contamination under the
oversight of the Los Angeles Regional Water Quality Control Board.
As part of its
ongoing operations, the City undertakes environmental assessment,
investigation, and monitoring activities of the Corporate Yard site. This requested authorization will extend
these highly specialized and technical services during the period that staff
re-bids and awards a new contract. The
recommendation to extend this contract with ICF is based on their technical
expertise and knowledge of the subject sites and will assure the continuation
of required services without interruption.
BUDGET/FISCAL IMPACT
The contract
amendment to 127(CD) totals $54,990.
Funds for the scope of services at the Corporate Yard are available in
the amount of $54,990 in CIP Account No. C250020.589000.
RECOMMENDATIONS
This report
recommends that the City Council authorize the City Manager to negotiate and
execute an amendment with ICF Consulting to Contract #127(CD) in the amount of
$54,990 for extending the existing agreement associated with
environmental investigation and remediation services at the City Corporate
Yard.
Prepared by: Craig Perkins, Director,
Environmental and Public Works Management
Brian Johnson, Environmental
Programs Manager
Richard Berman, Sr. Environmental
Analyst