City Council
Meeting: May 8, 2007
Agenda Item:
1-D
To: Mayor and City Council
From:
Subject: Award Contracts for the Downtown
Advanced Traffic Management System Communication and Traffic Signal
Modification Project
Recommended
Action
Staff recommends that the City Council
authorize the City Manager to:
1. appropriate $900,000 from revenue account 4.342.312 to the
traffic signal upgrade CIP account C040407.589202; and,
2. award a construction contract to KDC Inc. dba Dynalectric,
in the amount $3,194,900 plus a 10% contingency, for a total contract amount of
$3,514,390; and,
3. authorize the City Manager to negotiate a professional services agreement with PSOMAS for construction management services for the project, in the amount $404,000 plus a 10% contingency, for a total contract amount of $444,000, and
a.
amend
agreement No. 8497 (CCS) with Meyer, Mohaddes Associates in an amount of
$38,000, for a total not-to-exceed exceed amount of $177,008, including 10 %
contingency, and
b.
amend
agreement No. 1085 with RBF Consulting in an amount of $58,900, for at total
not-to-exceed amount of $110,700, including 10% contingency, and
c.
amend agreement No. 1100 with Kimley-Horn and
Associates in an amount of $18,000, for a total not-to-exceed amount of $43,644,
including 10% contingency, and
5. authorize the City Engineer to issue any
necessary change orders to complete additional work within budget authority.
Executive
Summary
A multi-phased plan
to implement the Advanced Traffic Management System (ATMS) citywide was
presented to City Council in June 2006.
Since then, the phasing plan has been concentrated into five phases as
noted in Attachment A Phase 1 was
completed in June 2006 and focused on
The current Phase 2
project, scheduled to be completed in fall of 2008, is critical to addressing
downtown congestion and will also implement the first of the transit priority
corridors within the City. The project
will install fiber optic communication and other equipment to facilitate
detection, coordinate traffic flow and accommodate transit priority. It includes modifications and upgrades to eleven
traffic signal locations in the downtown area.
The contract will also improve five intersections outside of downtown,
including implementation of required mitigation measures for the Public Safety
Facility, the Civic Center Parking Structure and the Main Library.
Contract actions
include award of a construction contract with KDC
Inc. dba Dynalectric, authorization for construction management services with
PSOMAS, and amendments to three existing design contracts for design and
construction review services. This project is funded through
grants, development mitigation fees and general funds.
Discussion
Background
The implementation of the Advanced Traffic Management System
(ATMS) will allow real-time management of the City of
Implementation of the citywide ATMS requires communication from
the
The City is receiving a $4.7 million grant form the Los Angeles County
Metropolitan Transportation Authority (Metro) to install equipment to enable
transit priority on the four current or future Rapid Bus corridors as indicated
in Attachment B. City staff has worked
with Metro and the Los Angeles Department of Transportation (LADOT) for the
past year to determine how to best facilitate transit priority along the Rapid
corridors while still maintaining local control. Design and construction of this system is
also incorporated into the project.
The Advanced Traffic Management System has been divided into a
multi-phased implementation plan, as described below, because of the tremendous
cost and management demands.
Phase 1: Phase
1 included the downtown section of
Phase 2 (Current
Phase): The contracts in
this report are to construct improvements in the downtown area bounded by, and
including, Ocean Avenue, Wilshire Boulevard, Lincoln Boulevard and Colorado
Avenue. Phase 2 also
incorporates
Phase 3: This
future phase will implement the Advanced Traffic Management and bus priority
system improvements along
Phase 4: Phase 4 condenses several
future phases to implement ATMS in the Office District area, the Mid-City area
and two other transit corridors,
Phase 5: Phase 5
will cover outlying areas such as San Vicente and streets north of that
corridor as the final phase in the implementation plan.
In addition to the construction
and construction management contracts, there are three existing design
contracts that require amendment. This
combined construction project originally consisted of three separate projects
designed by three different consultants with different types of expertise. Meyer, Mohaddes Associates was involved in
the development of the communications master plan, RBF Consulting was hired to
design the
Previous Council Actions
At its September 14, 2004 meeting, the City Council authorized the
purchase of an Advanced Traffic Management System from Siemens Energy and
Automation to provide the City central traffic signal control. At its July 26,
2005 meeting, the City Council authorized a design agreement with Meyer,
Mohaddes Associates for the preparation of fiber optic communication plans for
the downtown ATMS.
Contractor/Consultant Selection
The City published a Notice Inviting Bids for the construction
contract in the Los Angeles Times and the Santa Monica Daily Press
on March 2 and 3, 2007. Bid packages
were requested by twelve contractors and sub-contractors, and the City Clerk’s
office received five sealed bids which were publicly opened on April 2, 2007 by
the Deputy City Clerk. The five bidders
were:
|
Bidder |
Total |
|
KDC Inc. dba Dynalectric |
$3,194,900 |
|
Terno, Inc. |
$3,327,665 |
|
CSI Electrical |
$3,758,181 |
|
Comet Electric Inc. |
$4,479,754 |
|
Golden State Utility Co. |
$4,585,395 |
Engineer’s Estimate $3,316,202
Bids were evaluated based on competitive pricing, direct experience
on similar projects, qualifications in respect to ability, capacity, skill to
complete the work, green materials, the ability to perform the service
promptly, financial resources, reputation, and the ability to provide future
maintenance if needed.
Staff recommends KDC Inc. dba Dynalectric, as the best bidder
based on their price, quality of service offered, and experience with similar
projects including the City of
City staff contacted the agencies representing these projects, and
all respondents reported that the contractor’s quality of work was very good
and that the work was completed in a timely and cost-efficient manner. Staff also contacted the Center for Contract
Compliance and found that KDC Inc. dba Dynalectric, in good standing and
capable of handling labor compliance issues.
The California Contractor’s State License Board verified that the
Contractor’s license is active and in good standing.
Construction Management
Staff recommends construction management to be provided by
PSOMAS. In July 2006, the
City requested statements of qualifications for construction management
services for eight upcoming construction projects in the City, including the
Downtown ATMS Communication and Traffic Signal Modification Project. Ten firms submitted statements of
qualifications. City staff reviewed the
proposals and recommended interviewing four firms. Representatives from Civil Engineering and
Architecture Division and
PSOMAS is recommended as the top ranked firm to provide
construction management services for the construction of this project. These services include construction oversight
and continuous inspection of the contractor’s work during construction of
traffic signals and fiber optic lines; managing traffic control and detour
plans; reviewing submittals and change order requests; conducting periodic
progress meetings; providing information to the contractor on an as-needed
basis; and maintaining all necessary project documentation relevant to the work
conducted during construction. PSOMAS staff has much relevant experience such
as the Cal State Long Beach University Fiber Optic Telecom Infrastructure
Upgrade, City of
Budget/Financial Impact
Appropriate
a total of $900,000 from Revenue Account 4.342.312 (Playa Vista Mitigation) to
Account C040407.589202 as part of this Council action.
Funds
are available from the following accounts for the Downtown Advanced Traffic Management
System Communication and Traffic Signal Modification Project:
Account No. Project Element $
Amount
C010407.589201 Traffic Signal GF $1,210,247
C040407.589202 Traffic Signal Playa
C040407.589203 Traffic Signal Office District $ 168,925
C040407.589204 Transit Signal Other
$ 157,400
C200407.589205 Traffic Signal Ocean Av $ 295,560
C200407.589206 Traffic
Signal Transit Priority $ 1,377,531
TOTAL Phase 2 $
4,073,290
Prepared by:
Attachments:
|
Approved: |
|
Forwarded to Council: |
|
|
|
|
|
Eileen
Fogarty , Director, Planning & Community Development |
|
P. City Manager |