City Council
Meeting: May 8, 2007
Agenda Item: 1-E
To: Mayor and City Council
From: Craig
Perkins, Director - Environmental and Public Works Management
Subject: Modification
to Contract No. 8617 (CCS) with Fleming Environmental, Inc. for Additional
Underground Storage Tank Upgrades
Recommended
Action
Staff recommends that the City
Council authorize the City Manager to execute a modification to Contract No.
8617 (CCS) with Fleming Environmental, Inc., in an amount not to exceed $8,872
to provide additional improvements to the underground storage tank systems at various City Operations.
Executive
Summary
In addition to serving as the local agency for the underground
storage tank program implemented City-wide, the City is also the owner and
operator of 17 underground tanks at eight locations within the City. Since the Contract No. 8617 (CCS) was
executed on September 11, 2006, the Environmental Programs Division and contractor
identified enhancements to the monitoring equipment proposed for Fire Stations
#1, #2, and #5, and the Corporate Yard to assist City staff in operation of
their respective tank systems. In
addition, construction related improvements were also identified after the
contract was awarded; specifically, the dispensing operations at Fire Station
#1, piping replacement at Fire Station #3, and installation of electrical
conduit at Fire Station #5. These
improvements, while not mandated, will provide better fueling and avoid
potential repair and/or replacement in the future. The recommended Council action will authorize
new contract authority with Fleming
Environmental, Inc. in the amount of $417,770.
Funds in the amount of $8,872 for this contract modification are
available in the Underground Tank Management CIP account number C010020.589000.
Discussion
Background
On July
25, 2006, the City Council approved Contract No. 8617 (CCS) with Fleming
Environmental, Inc., to provide various underground storage tank improvements
at City-owned facilities in the amount of $371,725 plus a 10% contingency of
$37,173 for a total cost not to exceed $408,898. During implementation of
the approved modifications, additional upgrades were identified to provide a
higher standard of electronic monitoring at Fire Stations #1, #2, and #5, and
at the Corporate Yard in addition to providing consistency among City
operations. The dispensing equipment at Fire
Station #1 was relocated to better utilize space in the back lot and improve
fueling operations. Existing electrical conduits were not able to be used
during tank modifications at Fire Station #5; therefore, new conduits were
installed. Also, new piping associated
with the emergency generator at Fire Station #3 is proposed to be installed. The 10% contingency originally awarded is not
enough to cover the cost of these items, requiring an increase to the contract
of $8,872 for a new total not to exceed amount of $417,770.
Budget/Financial Impact
Funds in the amount of $8,872 are available in the Underground Tank
Manage CIP account number C010020.589000.
Prepared by:
Monica Hanley, Environmental Compliance Specialist
|
Approved: |
|
Forwarded to Council: |
|
|
|
|
|
Craig
Perkins Director
– Environmental and Public Works Management Department |
|
P. City Manager |