City Council
Meeting: August 14, 2007
Agenda Item: 1-J
To: Mayor and City Council
Chairperson
and Redevelopment Agency
From:
Subject: Award of Contracts for 2nd
and 4th Streets Pedestrian
and Streetscape
Improvements
Recommended
Action
Staff
recommends that the City Council:
1. award a construction contract to Griffith
Company, the best bidder, in the amount of $7,248,650 plus a 5% contingency,
for a total amount not to exceed $7,611,083;
2. authorize the City Manager to
negotiate and execute a professional services agreement with PBS&J Company
for construction management services, for a total amount not to exceed
$600,000;
3. authorize the City Engineer to
issue any necessary change orders to the construction contract to complete
additional work within budget authority;
4. authorize the City Manager to
execute a Cooperation Agreement between the City and the Redevelopment Agency
for costs associated with the 2nd and 4th Streets
Pedestrian and Streetscape Improvement Project; and
5. adopt a resolution finding that
the proposed improvements are of benefit to the Earthquake Recovery
Redevelopment Project Area.
Staff
recommends that the Redevelopment Agency:
1. authorize the Executive Director to execute a Cooperate Agreement
between the City and the Redevelopment Agency for payment of costs associated
with the 2nd and 4th Streets Pedestrian and Streetscape Improvement Project;
and
2. adopt a resolution finding that the proposed improvements are of
benefit to the Earthquake Recovery Redevelopment Project area.
Executive Summary
The 2nd
and 4th Streets Pedestrian and Streetscape Improvements
Project covers the eight blocks between Wilshire Boulevard and Colorado Avenue and
includes the installation of an additional 139 new Ginkgo
trees, removal of 54 existing ficus trees, new closely-spaced pedestrian
lighting to illuminate the sidewalk area, the
enlargement of tree-wells and the addition of decorative uplighting to the ficus
trees, enhancement of the six mid-block crosswalks on 2nd and
4th Streets, accessibility improvements and repair of ficus tree
damaged sidewalks and curbs. Council approved the project design,
including the removal of some trees, on October 11, 2005. As the result of a subsequent review by the
new Planning and Community Development Director in late 2006, the total number
of trees proposed to be removed was further reduced.
Staff recommends that the construction
contract be awarded to Griffith
Company, the best bidder. Funding for this project is from various
sources, including $1,836,000 in Federal Transportation Enhancement Activities
funds which must be awarded by August 30, 2007, or the funds will expire. The final project design that was submitted to
Caltrans for review and approval cannot be modified or the grant funds will be
forfeited.
Discussion
Background
On October 11, 2005, City Council conceptually approved the schematic design for 2nd and 4th Streets that included the new closely spaced pedestrian lighting similar to the Transit Mall fixture, curb extensions at the mid-block crosswalks to provide greater visibility and shorten the exposure of pedestrians to traffic while crossing the streets, replacement of alternating ficus trees with two Ginkgo trees, ficus tree uplighting, curb ramp accessibility improvements, and repair of tree damaged sidewalks and curbs. (See Exhibits)
The project
is located on 2nd and 4th Streets from
Public Outreach
Community workshops were held on April
4th and 9th, 2005, to explore and
reconfirm the vision for the project. Workshop invitations were sent directly to all
business owners, residents and property owners within the downtown area and the
workshops were advertised in three local papers. A survey was distributed at the community
meetings and to anyone who was not able to attend a meeting but wanted to voice
an opinion. Input was also gathered from
the Bayside District and the Santa Monica Chamber of Commerce at their monthly
meetings.
Subsequent to the City Council
approval of the schematic design in October 2005, staff proceeded with the
detailed design phase of the project and refined the tree placement plan. Individual trees were evaluated and it was
determined that an additional 8-9 of the larger “specimen” trees could be
retained and still provide the spacing necessary for the pedestrian lighting
and other amenities. Of the
approximately 181 total street trees in the project area, 106 remain; 31 ficus
trees will be removed and replanted elsewhere in the City; 23 of the ficus trees
that have been identified as diseased, beyond their useful life or unable to
survive a transplant, will be removed and converted to compost; and 21 palm
trees will be removed and relocated within the City.
Contractor Selection
Notice Inviting Bids were
published in the Santa Monica Daily Press on
Wednesday May 16, 2007, and Thursday May 17, 2007, and the bid package was sent to nine public
plan rooms. The
Notice Inviting Bids was also posted on the Civil Engineering and Architecture
Division’s webpage. Nineteen contractors requested bid packages, five companies attended the pre-bid job walk, and one sealed bid
was received by the City Clerk’s office and publicly opened on June 19, 2007,
by the Deputy City Clerk. Only one bid
was received as follows:
|
Company Name |
Bid Amount |
|
Griffith Company |
$7,248,650 |
The one
bid that was received is approximately $400,000 greater than the Engineering
estimate used for project budgeting purposes.
The bid was evaluated based on Federal grant requirements
per Caltrans. The Federal grant requires
that the contract be awarded to the lowest responsible bidder. The grant administrator, Caltrans, verified
that a single bid qualifies as the lowest responsible bidder. The bid documents required documentation of
at least three projects similar in nature to the 2nd and 4th
Streets Pedestrian and Streetscape Improvements Project.
Griffith
Company supplied the City with the names of previous similar projects. These projects include the Incline Baggage
Screening Project (
Construction
Management Selection
The City
requested Statements of Qualifications for construction management services on
July 19, 2006. Ten firms submitted
Statements of Qualifications, which were reviewed and rated by Environmental
and Public Works Management (EPWM) staff.
Selection criteria included direct experience on similar projects,
staffing efficiency, cost of services, technical competence, understanding of
the project’s scope, approach to the work, qualification of proposed staff, and
the ability to meet required time frames. The top four firms qualified
for the 2nd and 4th Streets Pedestrian and Streetscape Improvements Project were
invited to interview with the City.
Staff from EPWM interviewed the four firms on February 27 and 28, 2007. PBS&J Company is considered the top ranked
firm.
PBS&J
Company is recommended to provide construction management services. Their services will include construction
oversight and continuous inspection of the contractor’s work during demolition,
tree relocation, locating underground utilities, sidewalk construction,
lighting systems installation, managing traffic control and detour plans,
reviewing submittals and change order requests, conducting weekly progress
meetings, providing information to the contractor on an as-needed basis, and
maintaining all necessary project documentation relevant to the work conducted
during construction. PBS&J Company
has relevant experience working on streetscape and sidewalk projects for the
City of Dana Point and street resurfacing, bike-lane and pedestrian walkway projects
for the City of Del Mar.
Redevelopment Considerations
To authorize the use of Redevelopment
funds for the Project, the City Council and Agency must make the appropriate
determinations as required by the State of
Budget/Financial Impact
In
December 2006, the California Transportation Commission authorized an
eight-month extension of the $2.169 million Federal Transportation Enhancement
Activities (TEA) grant the City obtained from Metro (approximately $300,000 of
this amount has already been spent during the design process). If the construction contract for the project
is not awarded prior to the end of August, this entire grant amount will be
forfeited. The City also applied for
supplemental TEA funding in the amount of $762,000. However, it has not yet been decided by
Caltrans whether the entire supplemental grant amount can be used for the
project due to restrictive Federal requirements. City staff does not know when Caltrans will
make their final determination on the supplemental TEA funding.
As a
result of a bid that came in higher than the Engineer’s estimate, the potential
loss of the $762,000 in TEA supplemental grant funding, and a significant
number of bid items that are ineligible under Community Development Block Grant
and Prop A and C regulations, it is recommended that the budget shortfall be
made up through the use of Redevelopment Agency funds. If the City receives all or a portion of the supplemental
TEA grant funds, the Redevelopment Agency commitment will be reduced by an
equal amount. As a result of City
Council direction at the time of concept design approval, staff explored
alternatives for funding including possible assessment to the improvement
district. Although not a part of this
proposed action, staff and the Bayside District Corporation are looking into
additional assessments for other capital projects in the district.
Funds
are available in the following accounts:
Account
Number Source of Funding Amount
C200646.589010 Proposition A $ 80,000
C200646.589020 Proposition C 968,102
C190646.589000 CDBG 2,027,347
C200464.589000 TEA Grant Funds 1,797,393
C010456.589000 General Fund 301,263
C010646.589000 General Fund 506,382
C170776.589000 Redevelopment Agency 2,530,596
Total: $8,211,083
Prepared by:
|
Approved: |
|
Forwarded to Council: |
|
|
|
|
|
Director - Environmental
and Public Works Management Department |
|
P. City Manager |
Attachments: City
Council Resolution
Redevelopment Agency Resolution