Subject: Recommendation to Appropriate the Big Blue Bus Capital Budget and
Operating Enhancements, Approve Interim Positions during Campus Expansion
Construction and Increase Passenger Revenue from the Mini Blue Program
Recommended
Action
This staff report recommends the following
changes to the Big Blue Bus FY2007-08 budget:
1. appropriate $390,800 increase to Salary and Wage budgets,
2. authorize personnel increases of 7.0 permanent full-time
equivalent (FTE) and 6.0 limited-term FTE staff,
3. appropriate a capital improvement program budget of $16,423,166,
and
4. increase in
passenger revenue in the amount of $414,427.
Executive
Summary
During the Budget Study session on May 22, 2007 and subsequent
adoption on June 12, 2007, it was conveyed to Council that staff would come
back for recommended budget actions for Big Blue Bus (BBB) FY2007-08 proposed Capital
Improvement Program (CIP) budget and operating budget
enhancements when the final funding marks were
received from the Los Angeles County Metropolitan Transportation Authority (Metro). The final draft was
approved and released on July 26, 2007.
The Proposed Capital Improvement
Program covers Fiscal Years 2008 to 2010. Although the program spans three
years, staff requests only the first year be appropriated for a total of $16.4
million. The appropriation will provide funds for bus replacement, bus
components, bus stop amenities, facility upgrades and renovation, yard
improvements, service vehicles, transit mall maintenance, and technology and
telecommunications equipment, all of which are essential to day-to-day bus
operations and infrastructure and equipment replacement and maintenance.
Ongoing operating budget
enhancements include 6.0 FTE Motor Coach Operator positions for the Mini Blue operations
and 1.0 FTE Motor Coach Operator Supervisor position for vacation relief and dispatch
operation restructuring. These positions
are required for the new Mini Blue program and the overall bus operations.
An additional 6.0 FTE limited-term
positions are requested to assist in the off-site operations during the
construction of the BBB Maintenance Facility, where 15 to 30 buses will need to
operate from a remote facility. As these
positions are created exclusively for the construction of the Campus Expansion
project, they will be funded by the capital improvement budget.
In FY2007-08, the BBB will receive fare reimbursement payments from
Santa Monica College (SMC) in the amount of $414,427 as a result of the transit
partnership between the two agencies. On all routes supported through the SMC
Partnership, SMC ID cardholders board for free by showing their identification
card to the driver. All the services supported by SMC are open to the public
paying the appropriate fare.
Discussion
In developing its CIP budget for FY2007-08, the BBB used the final
funding marks made available by the Los Angeles County Metropolitan Transit
Authority (Metro), where federal, state and local subsidies are allocated to
fund ongoing and one-time projects. A listing of CIP projects with sources of
funding is presented as an attachment to this staff report.
The BBB selectively added positions to meet critical needs.
Council recently approved BBB service modifications to implement the new Mini
Blue Service Plan designed to respond to Council and community requests for
environmentally friendly transit alternatives within
The BBB reorganized its communications and on-street operations
supervision as part of its Advanced Fleet Management System implementation. The reorganization necessitated 1.0 additional
FTE Motor Coach Supervisor position. This
position will be responsible for monitoring quality control for the on-street
service using the new dispatch system with advanced technology communications. It will also provide vacation relief and
additional supervisory support in dispatch to handle absences, bus assignments,
regulation adherence and other operator issues requiring
supervisory authority.
The construction of the BBB Maintenance Facility will begin in
September 2007 and is projected to be completed in the first half of 2010. During this period, daily operations will
continue at the bus yard. However, 15 to
30 buses will be diverted to a remote parking facility to accommodate the
construction activities at the bus yard. The implementation of the remote site
operations requires 6.0 FTE limited term positions including
1.0 FTE Mechanic, 2.0 FTE Yardmaster and 3.0 Motor Coach FTE Cleaner positions. These limited term positions expire June 30,
2010.
Budget/Financial Impact
Appropriations are required for the proposed FY2007-08 BBB Capital
Improvements Program and the operating enhancements of 6.0
FTE Motor Coach Operator and 1.0 FTE Motor Coach Operator Supervisor positions as
listed below:
Capital Improvements Program:
|
Account |
Project
Description |
Amount |
|
C410006 |
Telecommunication
Services |
$
43,340 |
|
C410006 |
Bus Components |
3,686,906 |
|
C410107 |
Yard Improvements |
320,000 |
|
C410113 |
Technology Equipment |
1,287,960 |
|
C410114 |
Bus Stop
Amenities |
3,297,000 |
|
C410115 |
Service Vehicles |
330,000 |
|
C410458 |
Transit Mall |
322,500 |
|
C410519 |
Bus Replacement |
5,822,960 |
|
C410709 |
Shop Equipment |
60,000 |
|
C410826 |
Facility Upgrades
and Renovations |
500,000 |
|
C410749 |
|
677,500 |
|
C410099 |
Farebox |
75,000 |
|
|
Total: |
$ 16,423,166 |
For details see the attachment.
Funding for the capital improvement program comes from federal, state
and local agencies through the annual funding allocations administered by
MTA. Revenues are recorded when payments
are received on reimbursement of actual expenditures. Revenues are budgeted at capital
grant accounts in the year the reimbursements are projected to be received. The capital
revenue budget adopted in June for FY2007-08 reflects revenue from
reimbursements for capital projects approved in prior years. No additional budget adjustments are needed.
Operating enhancements:
|
Division |
Description |
Amount ($) |
|
Transit Services |
6.0 FTE Motor
Coach Operator positions |
307,100 |
|
Transit Services |
1.0 FTE Motor
Coach Supervisor position |
83,700 |
The 6.0 FTE Motor Coach Operator positions ($307,100) can be
fully funded by the Mini Blue revenue increases ($414,427), while the 1.0 FTE
Motor Coach Supervisor position ($83,700) will be funded by the MTA funding
allocations.
The 6.0 FTE limited term positions ($443,400) for
the remote site operations will be funded by the Campus Expansion CIP (account
C410104.589100), which has sufficient funds in FY2007-08 to cover these
positions. Future appropriations will be
evaluated in the annual CIP budget process and included in the Proposed Budget for
Council’s review and adoption.
Passenger Revenue account (41642.402000) will be increased by
the receipt of $414,427 from the SMC for the Mini Blue program.
Prepared by:
|
Approved: |
|
Forwarded to Council: |
|
|
|
|
|
Carol
Swindell Director
of Finance |
|