City Council Meeting: December 11, 2007

Agenda Item: 8-B

To:                   Mayor and City Council

From:              Craig Perkins, Director – Environmental and Public Works Management

Subject:          Approval of Concept Design for the 20th Street and Cloverfield Boulevard Street Improvements Project; and Authorization of a Contract Modification for Design of Street Light Circuit Conversions and Traffic Signal System Modifications

 

Recommended Action

Staff recommends that the City Council:

1.   approve the concept design for the 20th Street and Cloverfield Boulevard Street Improvements Project; and

2.   authorize the City Manager to negotiate and execute a modification to Contract No. 8581 (CCS) with Ahbe Landscape Architects in an amount not to exceed $99,100, for the design of street light conversions and traffic signal modifications for the Project.

 

Executive Summary

The 20th Street and Cloverfield Boulevard Street Improvements Project (Project) provides various streetscape enhancements on 20th Street and Cloverfield Boulevard, between the Santa Monica Freeway (I-10) and Pico Boulevard.  Following several community meetings, the attached concept design has been developed to address safety, traffic and aesthetic improvements on these major thoroughfares.  The concept design includes planting of new trees and parkway landscaping, installation of pedestrian lighting, installation of colored concrete sidewalk sections, curb extensions on Cloverfield Boulevard, traffic signal modifications and streetlight circuit upgrades.  The proposed streetscape improvements along Cloverfield Boulevard will reduce the amount of existing street parking.

 

Several improvements proposed in the concept design, including street light circuit upgrades and traffic signal modifications, were not considered part of the original scope of work contemplated for this project but have been included to respond to community concerns.  To include this scope of work requires modifying the professional services agreement with Ahbe Landscape Architects to add the design of street lighting circuit conversions from series to multiple and traffic signal upgrades and modifications consistent with the project concept.  With this amendment, the agreement will be increased by $99,100 and is not to exceed $549,100.  Funds are available in the project budget to cover this proposed amendment.

 

Discussion

In 2001, a feasibility study to improve 20th Street and Cloverfield Boulevard between I-10 and Pico Boulevard was prepared.  At that time, preliminary design concepts were developed but not reviewed with the Pico community stakeholders.  Ahbe Landscape Architects was procured under Contract No. 8581 (CCS) for the design of 20th Street and Cloverfield Boulevard Improvements Project.  Using the feasibility study as basis of the preliminary concept design, their first task was to develop a community involvement program to maximize participation from local stakeholders in the development of the design concepts for this project.  A series of public workshops were conducted to solicit ideas and concerns from the community and to build a consensus on the final design concepts for the project.  Based on community input, a concept design has been developed which consists of elements to improve pedestrian accessibility and safety and aesthetics along these thoroughfares. 

 

The concept design includes planting of new trees and parkway landscaping, installation of pedestrian lighting, installation of colored concrete sidewalk sections, curb extensions on Cloverfield Boulevard, traffic signal modifications, and streetlight circuit upgrades.  The concept design considered the addition of crosswalks at various locations to improve pedestrian safety.  A study evaluating additional crosswalks was performed.  Additional crosswalks at unsignalized locations were not recommended since the proposed crosswalks would not improve pedestrian safety. 

 

One of the key elements of the concept is the installation of curb extensions along Cloverfield Boulevard.  Implementing curb extensions will reduce the number of existing street parking spaces.  The curb extensions are intended to improve the pedestrian experience by providing a buffer area for parkway landscaping between the sidewalk and street.  Curb extensions must encroach into the street parking lane since the existing sidewalk is too narrow to accommodate both an accessible walkway and landscaped parkway.  Due to the proposed curb extensions, a maximum of nineteen of forty-one existing street parking spaces on Cloverfield Boulevard may be eliminated.  The existing parking spaces on the east side of the street may be reduced from twenty to eleven.  The existing parking spaces on the west side of the street may be reduced from twenty-one to eleven.  It may be possible to maintain one or two additional parking spaces depending on adjustments to the limits of the curb extensions that will be made during the preparation of bid documents.

 

The conceptual design indicating reduced parking on Cloverfield Boulevard was presented to the community at the August 14, 2007 meeting.  The community expressed concerns with the loss of parking.  The potential loss of parking spaces was discussed with several residents as the trade-off for the implementation of the streetscape project on Cloverfield Boulevard.  Residents understood that the implementation of landscaped curb extensions would reduce the availability of street parking; however, they indicated that if possible, the loss of street parking should be minimized.  A survey of parking availability was conducted on October 25, 2007.  It was recorded that some blocks of Cloverfield Boulevard and adjacent streets occasionally have no available parking at various times during the day.  Additionally, the pending affordable housing project at High Place proposes the elimination of additional on street parking approximately 500 feet east of Cloverfield Boulevard.  The number of parking spaces on 20th Street does not change since no curb extensions are proposed. 

 

During the public workshops, the community expressed concerns about pedestrian lighting and street lighting in the project area.  In order to provide enhanced lighting in the project area, an upgrade to the existing series streetlight circuit is necessary.  Additionally, traffic signal equipment in the project area requires upgrades to be consistent with the future Citywide Advanced Traffic Management System.  The traffic signals at the intersection of the Santa Monica Freeway off-ramp and 20th Street and the intersection of Pico Boulevard and 20th Street require complete upgrades.  Minor traffic signal modifications are also required due to the proposed street improvements at the intersections of Delaware Avenue and 20th Street, Santa Monica Freeway on-ramp and Cloverfield Boulevard, and Virginia Avenue and Cloverfield Boulevard.  The upgrades to the street lighting circuit and a portion of the traffic signal modifications are not part of the original scope of work contemplated for this project.   

 

The current preliminary cost estimate to construct these additional streetlight and traffic signal upgrades is $1,200,000.  These upgrades, requested by the community, increased the total project cost to approximately $6,700,000.  During the design development and bid document phase, staff will identify funding options for these additional upgrades as well as project scope reduction options to bring the cost in line with current available funding.  At this time, it appears that the source of additional funds could come from other existing CIP projects, but may also require some additional General Fund appropriations.

 

Previous Council Actions

On April 25, 2006, City Council approved a contract with Ahbe Landscape Architects, Contract No. 8581 (CCS), in an amount not to exceed $450,000 for the design of 20th Street and Cloverfield Boulevard Street Improvements Project. 

 

Public Outreach

Three public workshops were held at the Virginia Avenue Park on November 16, 2006, January 11, 2007, and August 14, 2007.  The first two workshops included both an afternoon youth session and an evening public session.  A public notification program was conducted to raise awareness of the project in the adjacent neighborhoods and to encourage participation in the workshops.  A total of sixty-four community members attended the meetings.  The following media sources were used to inform the residents, businesses, and property owners about the public workshops:

 

·        Radius Mailer: A bilingual (English/Spanish) meeting flyer was mailed to approximately 1500 residents, businesses and property owners.  A special flyer designed to encourage attendance at the youth meeting was also distributed at the Virginia Avenue Park Teen Center.

·    Grassroots canvassing:  The project’s public relation consultant team canvassed the community on January 5, 2007, largely focusing on the local businesses and storefronts.  On January 6, 2007, additional canvassing focused on Virginia Avenue Park users and patrons of the Virginia Avenue Park Farmer’s Market.  In addition, flyers were handed out at Virginia Avenue Park and notices were posted in storefronts.

·    Phone calls:  Phone calls were made to the Pico Improvement Organization, Pico Neighborhood Association, Virginia Avenue Park Advisory Board, and to Edison and Grant Elementary schools.  Both the Pico Improvement Organization and Pico Neighborhood Association distributed the flyer via email and at their regular meetings.  In addition, both schools posted the flyer on their respective Parent Teacher Association website.

·    Media advisory:  A media advisory was developed and sent out by the City to local broadcast and print media including The Ocean Park Gazette, The Mirror, The Argonaut Newspaper, The Lookout, Santa Monica Daily Press, and KCRW Public Radio Station.  Meeting information was also posted on the City's website.

 

 

Financial Impacts & Budget Actions

Funds in the amount of $99,100 are available in account number C010522.589000 (Feasibility & Prelim Dsgn 20th).  Potential increased maintenance costs associated with these improvements will be evaluated during final design.

 

Prepared by:  Mark Cuneo, P.E., Principal Civil Engineer


 

 

 

Approved:

 

 

 

Forwarded to Council:

 

 

 

 

 

Craig Perkins, Director

Environmental and Public Works Management Department

 

P. Lamont Ewell

City Manager

 

 

 

 

 

Attachments:              1.   Cloverfield Boulevard, Concept Plan, South

                                    2.   Cloverfield Boulevard, Concept Plan, North

                                    3.   20th Street, Concept Plan, South

                                    4.   20th Street, Concept Plan, North

                                    5.   Plant Materials