Recommended
Action
Staff recommends that the City Council authorize the
City Manager to negotiate and execute a 2nd modification to
Professional Services Agreement No. 8353 (CCS) with Zimmer Gunsul Frasca, in an
amount of $50,000 bringing the total contract amount not to exceed $572,700.
Executive Summary
The 2nd and 4th
Streets Pedestrian Streetscape Improvement Project (Project) consists of eight
blocks of pedestrian and streetscape improvements along 2nd and 4th
Streets between
Discussion
On
June
22, 2004, City Council authorized Professional Services Agreement No.
8353(CCS) with Zimmer Gunsul Frasca for design of the Project in the amount not
to exceed $483,000. On October
11, 2005 City Council authorized a modification to the Professional
Services Agreement in the amount not to exceed $39,700; and approved proposed
schematic design elements for the 2nd & 4th Streets
Pedestrian Streetscape Project. The
original scope of work was enhanced to include structural soil for newly
planted trees and mid-block crosswalks. The
report discussed tree up-lighting and a funding source for design development
of the tree up-lighting was not identified.
Staff authorized design development of the
tree up-lighting using $28,000 from the existing design agreement. Additionally, due to delay in construction
from the ficus tree restraining order, costs for construction support design
services are anticipated to increase by $22,000. To accomplish this work, an additional authorization
of $50,000 is required.
Financial Impacts
& Budget Actions
Second
modification to Contract No. 8353 (CCS) will include additional design services
in the amount of $50,000. The modified agreement
will not exceed $572,700. Funds in the
amount of $28,000 are available in C010646.589000 (Pedestrian Extension 2nd
&
Additional grant funds in the amount of $762,000 will be appropriated into the project budget as part of the June final budget adoption. These grant funds will be applied towards the project’s construction budget.
Prepared by:
|