Project Name: Parking Structures 1-6 Façade Improvement Project
|
Project
Location: |
From |
To |
|
Parking Structure #5, 1440 4th Street |
|
|
|
Parking Structure #2, 1235 2nd Street |
|
|
|
Parking Structure #4, 1321 2nd Street |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Scope: This project entailed repainting, maintenance repairs, and planter removal at the existing downtown parking structures 1-6. Painting work is complete in all structures. Artwork installation work is ongoing in parking structures #4 and #5. Expect delays upon exit.
Scheduled Start Date: 10/13/2008
Scheduled End Date: 11/20/2009
Scheduled Construction Time:
Detours: Artwork installation work is ongoing in Parking Structure No. 5. Expect delays upon exit.
Contractor Name: AWI Builders
Phone:
Project Manager: City of Santa Monica ( Alex Nazarchuk)
Phone: (310) 458-8721
Construction Manager: City of Santa Monica (Alex Nazarchuk)
Phone: (310) 458-8736
This page was last modified on 07/23/2008