Planning
Commission Meeting: June 20, 2007
Agenda Item: 11-A
To: Planning Commission
From: Eileen Fogarty, Director of Planning and Community
Development
Subject: Discussion and Recommendation to the
City of Santa Monica Redevelopment Agency on the Design Consistency of the
Proposed Santa Monica Place Remodel with the Downtown Redevelopment Plan.
Address:
Applicant: Macerich Company.
Recommended
Action
It
is recommended that the Planning Commission discuss the proposed project and convey
appropriate design recommendations to the Santa Monica Redevelopment Agency consistent
with Sections 410 and 422 of the Downtown Redevelopment Plan contained in
Attachment B.
Executive
Summary
The applicant proposes to remodel
the existing 676,181 square foot
In order to accomplish the
proposed remodel, the applicant proposes to demolish portions of fourth, fifth
and sixth levels of the parking decks
which are located in the northwestern corner of the Agency-owned parking
Structure Number 7, amounting to 63 parking spaces. The project will be submitted to both the
Redevelopment Agency and the City for review and approval. The Redevelopment
Agency review includes review of the CEQA analysis, for which an Initial Study
(IS) is currently underway, amendments to the existing legal documents
associated with the original construction of

The applicant is seeking
advisory design guidance from the Planning Commission prior to the Agency’s
consideration of the proposed project.
The City process will include review of an Administrative permit, and
Architectural Review Board approval (appeal able to the Planning Commission).
The Administrative Approval application was submitted on March 6, 2007, and the
project has already been subject to both pre-submittal and Planning design team
review in relation to integration and compatibility with the downtown.
Key issues that have been
discussed and refined in the pre-submittal design review include:
·
Revision of the
·
Design dialogue related to a concept plan for the as yet un-leased
former Robinson’s May site at the corner of
·
The proposed gross leasable area will be 548,322 square feet,
which is an approximate 10,000 square foot reduction from the current gross
leasable area.

The Planning Commission should
consider the proposed project and shape their discussion in relation to building
and urban design and overall project aesthetics with emphasis on:
Background
In the late 1970s, the Santa Monica
Redevelopment Agency entered into a Disposition and Development Agreement for
the creation of
During
2002, City staff and consultants worked with Macerich on a master plan for
revitalizing
In
January 2005, the City Council considered the conceptual Development Agreement proposal. Council chose not to move forward with
negotiations on the specific concept proposed and directed staff to work with
Macerich in an extensive community engagement process to hear ideas from the
community on what changes, if any, should be made to
During the summer of 2005, Federated
Department Stores (the parent company of Macy’s) announced the acquisition of
May
Project / Site Information
The project is sited in the
heart of the downtown. The current buildings were constructed in 1980, as a
means of revitalizing a struggling downtown. As was typical of mall design at
that time, the mall is internally focused, with minimal integration into the
surrounding context. The current proposal intends to change the focus, and
integrate the existing buildings with the downtown as much as possible within
the parameters of a remodel. As noted earlier, the project does not propose any
increase to height or square footage but is reducing the existing square
footage by approximately 10,000 square feet, and reconfigures the existing mall
within the same axial floor plan.
The principle design components
of the remodel are as follows:
Entrances:
Redesign of the four entrances
to promote a more welcoming pedestrian oriented and integrated design. Each
entrance intends to augment the character of its particular context.
·
The entrance from Broadway, across from the Third Street Promenade,
will be the most significantly changed, removing the roof from the current
façade line back to the center of the building, and re-configuring the store
fronts to create a continuation of the outdoor mall street frontage found on
Third Street. In order to accomplish this urban design component, the existing
food court will be relocated to the Third Floor, with the intent of providing
an ambiance of open space and views, as well as a providing a pubic accessible
urban gathering place associated with both counnter and table service
restaurants.

Entrance from Broadway
·
The

Entrance Entrance
From
·
The

Entrance From
·
The

Entrance from
Open Air
The project proposes to
partially convert the mall to an outdoor environment by removing the roof from
the northerly axis to provide a stronger connection to the Promenade.
Additionally portions of the roof in the mall interior would be removed
creating courtyards and pedestrian walkways that are open to the sky, benefiting
from natural ventilation and air circulation.
Food Service
As part of the effort to
strengthen the connection with the Third Street Promenade, the food court,
which is currently located on the northern axis that approaches the Promenade,
would need to be relocated to allow the architectural vocabulary of the existing
successful outdoor mall to extend into this site. The
Demolition of Portions of the Parking Deck
In order to complete the key
concept of opening the northern axis towards the Promenade, the project
requires that a portion of Parking Structure 7, a Redevelopment Agency-owned
parking structure, be demolished. The demolition would remove the portions of
the garage over the food court and retail space. Approximately 63 parking
spaces will be removed. However, given the reduction of square footage of
approximately 10,000 square feet throughout the mall, and re-striping of
parking structures numbers 7 and 8, the project will comply with both Zoning
Ordinance and Redevelopment Plan parking standards.
Environmental
Analysis
The project is currently undergoing an Initial Study (IS) process. A
more intense version of the proposed project was previously studied under the
Civic Center Specific Plan EIR, and the proposed use involves a reduced project
as well as a reduction in square footage from the existing on-site use. Based on the findings of the Initial Study,
the appropriate CEQA process will be followed, including circulation for public
comment.
Project Analysis
Urban
Design & Neighborhood Compatibility,
In
reviewing the project for urban design and neighborhood compatibility staff has
worked with the applicant on the following design issues which have resulted in
revisions to the pre-submittal design:
·
Creating a focal
point for the termination of the connection to the Third Street Promenade
·
Clarifying the
grade change and pedestrian path of travel and redesigning the stairs on the
·
Envisioning the
most direct path of travel for the interior circulation in relation to placement of interior escalators.
·
Opening up the
retail to the
·
Designing a
conceptual program for the former Robinson’s-May site to emphasize pedestrian
orientation in compliance with the downtown urban design standards and creating
the standard for ensuring that the southeast corner of
The
applicant continues to work with staff on these key design components:
·
Refining the
design for the

·
Concepts for
additional articulation to the former Robinson’s-May building:
The
current design addresses staff recommendations to provide greater pedestrian
orientation at the significant corner of 2nd Stand Broadway, but further consideration
to design concepts to provide articulation and detail to the facades are
necessary.

Earlier concept
former Rob-May site

Current concept
former Rob-May site
Public Outreach:
In
addition to the early public outreach related to
·
Traffic in the
downtown
·
Visual and
pedestrian linkages from
·
Location of bathrooms
·
Economically
diverse retail
·
Public
transportation
·
Entrance design
While
most comments were in favor of the concept of revitalizing the mall and opening
it to the outdoors, several preferred the closed indoor mall.
Conclusion
Staff
supports the direction of the building design and relation to the urban context
as required by the Downtown Redevelopment Plan in that the design will improve
the integration into the downtown, create more inviting entrances and make a
better connection with the Third Street Promenade which is an anchor of the
downtown. Staff supports the concept of providing an urban courtyard and food
court with access to public views, better pedestrian connections between the
Civic Center area, Third Street and Santa Monica Place, and believes the
increase in pedestrian amenities associated with this re-model project will justify
the removal of a portion of the Agency owned parking structure while maintaining
adequate required parking. Staff seeks Planning Commission direction on
providing recommendations in relation to the former Robinson’s -May site and
refinement of the
Prepared
by: Sarah Lejeune, Senior
Planner
Attachments
A.
Public Notice
B.
Project
Proposal
ATTACHMENT A
|
|
NOTICE OF A PUBLIC HEARING BEFORE THE |
Design Discussion of Proposed Santa Monica Place Remodel
A public hearing will be held by the Planning
Commission for a design discussion of the proposed
The applicant
proposes to remodel the existing 676,181 square foot
Address:
Applicant: Macerich
Company.
DATE/TIME: WEDNESDAY, June
20, 2007 at 7:00 p.m.
LOCATION: City Council
Chambers, Second Floor,
MORE INFORMATION
If you want more information about this project,
please contact Principal Planner Paul Foley at (310) 458-8341, or by e-mail at Paul-Foley@SMGOV.net
The meeting facility is wheelchair accessible. For
disability-related accommodations, please contact (310) 458-8341 or (310)
458-8696 TTY at least 72 hours in advance. All written materials are available
in alternate format upon request. Santa Monica Big Blue Bus Lines numbered 1,
2, 3, 5, 7, 8, 9, and 10 serve City Hall.
ESPAÑOL
Esto es una noticia de una audiencia pública para
revisar applicaciónes proponiendo desarrollo en